Skip to content

Pipeline Connection Thrust Blocks, Cumbria

Catagory: Geotechnical Design, Groundwater Control

Location: Cumbria, UK

Client: O’Connor Utilities

Sector: Energy & Utilities

Temporary Groundwater Control for the installation of two new pipeline connections

The Main Contractor was engaged to make two new pipeline connections, each requiring the construction of a concrete thrust block at a location in West Cumbria.

OGI Involvement

The pipework connections and the construction of the thrust block structures were to be carried out within two excavations, one on the North Line, the second on the South Line. The excavations were 2-3m deep and were to be constructed with 45° batter embankments.

A high water table meant that there was a necessity to carry out dewatering to enable the excavations to proceed. The site was also prone to flloding during periods of heavy rainfall. Well points from a previous dewatering system nearby were left in place and therefore, could potentially be used again.

OGI Scope

Wellpoint Assessment

Assessment as to whether previously installed well points could be used to dewater the two new excavations, and to specify any additional requirements.

Settlement Analysis

Assessment of the level of settlement expected as a consequence of dewatering and to design safe stable embankments to enable the pipe connections and associated construction works to be completed.

Slope Design

Design of 45° battered slopes for the retaining embankment which satisfied the safety criteria of Eurocode 7. An Inspection, Testing and Monitoring Plan (ITM Plan) was developed and strictly followed during construction.

Wellpoint Design

OGI recommended the installation of a minimum of 42 new well points, to a depth of 5.9m bgl, to enhance the existing system to enable safe excavation of the new thrust blocks and connecting pipework.

After combining the shallow and deep aquifer, based on considered assumptions, OGI estimated a total potential settlement of around 6mm. However, as conservative assumptions were made it was anticipated that the actual settlement would be significantly less.

Have a project?
Let's work together

Call us on 0191 378 7010 or drop us a message with your enquiry

Enquire Now

Awards

The Dewatering Institute
Ground Engineering Awards 2020 Finalist
Ground Engineering Awards 2018 10th Anniversary Winner
Ground Engineering Awards 2017 Highly Commended
British Construction Industry Awards 2016 Highly Commended
The Dewatering Institute
Ground Engineering Awards 2020 Finalist
Ground Engineering Awards 2018 10th Anniversary Winner
Ground Engineering Awards 2017 Highly Commended
British Construction Industry Awards 2016 Highly Commended
The Dewatering Institute
Ground Engineering Awards 2020 Finalist
Ground Engineering Awards 2018 10th Anniversary Winner
Ground Engineering Awards 2017 Highly Commended
British Construction Industry Awards 2016 Highly Commended